Shanghai Metro Line 9

In 2002, MTR established a joint venture company Shanghai Hong Kong Metro Construction Management Co. Ltd. (SHKMCM) to undertake project management of railway construction projects in Shanghai. SHKMCM was appointed as Owner's Representative of project management, on behalf of the owner, being responsible for the design and construction of Shanghai Line 9 (Shensong Line). Meanwhile, SHKMCM was also appointed as an Owner's Advisor of the Line 8 (Yangpu Line) and Line 11 (Shenjia Line).

The Line 9 Phase I project is a 31 km (Tunnels 12 km, Viaducts 17 km, At-grade 2 km) metro line comprising 13 stations (Underground 9, Elevated 4) from Songjiang New Town Station to Yishan Road Station. It is split into 31 civil / building / ABWF and 23 E&M contracts/Sub-contracts. The total project cost is about RMB12.9 billion.

Shanghai Metro Line 9





:linkText:more
Project Progress - September 2008

Shanghai Metro Line 9 Phase I, from Songjiang New Town Station to Guilin Road Station, has opened for public service since 29 December 2007.

For Yishan Road Station, structure of entrance no. 1 was completed and entrance no.3 is in progress. Architectural finishing works were substantially completed at 2 underground floor levels and are in progress at another 2 floor levels. Equipment rooms have been progressively energized for equipment testing from July.

For tunnel section, down track overhead line has been energized from Guilin Road Station to Yishan Road Station. Other trackside installation works continues.


Vent Shaft Construction at Yishan Road Station

Wall Panel Installation at Yishan Road Station

Platform Screen Door Installation at Yishan Road Station
back top